How to calculate remaining units and the required daily rate

Formulas for achieved, remaining, required per day and the period-end projection, with a worked example. See which branch is behind before the month ends.

Published · 2 min read

The purpose of target tracking is to act before the period is over. For that, "what percentage have we done" is not enough: you need to know how many a day you need from today to reach target, and how the period will end at the current pace. Five simple formulas give you that.

The five formulas

QuantityFormula
Remainingmax(target − achieved, 0)
Required per dayremaining ÷ days left
Daily averageachieved ÷ days elapsed
Period-end projectionachieved + daily average × days left
Should have by todaytarget × days elapsed ÷ total days

Deviation from plan is achieved − should have by today. If it is negative you are behind plan.

A worked example

A branch’s home-internet target is 180 units, the period is 30 days and today is day 18. So far 70 units are done.

  • Remaining: 180 − 70 = 110 units
  • Days left: 30 − 18 = 12
  • Required per day: 110 ÷ 12 ≈ 9.2 units
  • Daily average: 70 ÷ 18 ≈ 3.9 units
  • Period-end projection: 70 + 3.9 × 12 ≈ 117 units
  • Should have by today: 180 × 18 ÷ 30 = 108 units; deviation 70 − 108 = −38

Reading it: at the current pace the period ends at 117 units (about 65% of target); to reach target the daily pace must rise from 3.9 to 9.2, more than double. Seen on day 18 you can still act; seen at month end you can only take notes.

A projection is not a guarantee

The projection carries the past pace into the future. A campaign, a holiday or stock can change the pace; read it as a signal, not a promise.

Label the status

Not everyone reads numbers; a status label does it for them. A simple rule is enough: a KPI that has reached target is "Completed", one with a small deviation is "On track", one whose projection falls under target is "At risk", and one whose required daily rate far exceeds the current pace is "Behind". A Branch Manager should see which KPI to focus on within seconds.

Look at branch and employee level

The company total can look fine while a single branch is behind. Applying the same formulas per branch and per employee shows who needs support. KPI target tracking does these calculations from transactions automatically; the effect of reaching target on commission can be followed on the commission calculation page.

Put this method to work in Primsis

Try it free for the first 3 months, or let us show in a demo how it runs across your own branches.

First 3 months free · no credit card required · monthly fee per branch, excl. VAT